POLICY AND ECONOMIC
OIL & GAS MARKET
Addressing the gathering, Dr. Neeraj Mittal, Secretary, Ministry of Petroleum and Natural Gas,
highlighted that India currently meets nearly half of its natural gas requirement through imports and
that CBG provides an opportunity to convert domestic organic waste into a domestic gas resource.
He said that the experience of the sector had also highlighted constraints relating to volatile revenues,
fragmented support, limited long-term policy visibility, feedstock assurance, organic manure offtake
and access to finance. GOBARdhan addresses these issues through the Ministry of Petroleum and
Natural Gas as the single nodal Ministry, predictable pricing, greater certainty of gas offtake,
enhanced capital assistance, consolidated processes and greater use of digital monitoring.
The Secretary also highlighted the important role of State Governments in translating the national
framework into projects on the ground, including through enabling State CBG policies, feedstock
assessments, suitable land banks, faster approvals and infrastructure support.
An integrated framework for the CBG sector
A presentation on GOBARdhan outlined the Scheme architecture and the transition from multiple
standalone interventions towards an integrated framework for the sector. GOBARdhan comprises six
key interventions: CBG Offtake Assurance, CBG Pricing Framework, Capital Assistance for CBG
Projects, Development of Pipeline Infrastructure, Credit Guarantee Support and the CBG Ecosystem
Challenge Fund.
Under the offtake framework, CBG plants will be mapped to identified City Gas Distribution
geographical areas or CBG clusters, enabling a dependable route to market. Under the CBG Obligation
(CBO), the obligation to procure CBG rests with City Gas Distribution (CGD) entities. The procurement
obligation has been prescribed at 3% in FY 2026–27, 4% in FY 2027–28 and 5% from FY 2028–29
onwards for the CNG (Transport) and PNG (Domestic) segment
The Scheme introduces an administered CBG price of ?2,110 per MMBtu, providing greater revenue
visibility to producers. Eligible greenfield projects can receive capital assistance of up to ?2 crore per
TPD of installed CBG capacity, including support for plant machinery, feedstock aggregation and
FOM/LFOM processing and manure value-addition equipment.
To address gas evacuation constraints, support of up to 80% of eligible capital expenditure is available
for pipelines connecting CBG clusters to trunk pipeline networks and up to 50% for standalone plants
connecting to CGD networks.
A dedicated credit guarantee mechanism for eligible MSME-based CBG projects will cover up to 85%
of the outstanding amount at default, subject to prescribed project limits. The guarantee cap is ?20
crore per project for general MSME projects and ?25 crore per project for women-led MSME projects,
providing enhanced support to women entrepreneurs in the CBG sector.